CW Neal Road Bridge #249B

Project No.:  1115235
Project limits:  CW Neal Rd - 1.5 miles south of SR-203
Project type:  Bridge
Thomas Bros. Map No.:  599e3

Project description

The CW Neal Road Bridge project will remove the existing bridge, and replace it with a new structure that conforms to current design standards, preserving existing road network function.

Why is King County doing this project?

The existing bridge has exceeded its useful life span.
 

Project management phase:  Project not yet started

Status as of November 17, 2014

Programmed to start in 2016. Construction anticipated to begin in summer 2018.

 

See also

Environmental compliance for bridge activities External link graphic
King County Annual Bridge Report
Overlegal truck permit
Road closures
Road standards
Roads' future - learn what's needed to preserve our road network
Seattle bridges External link graphic
Title VI information
WSDOT Historic Bridges External link graphic

How does the CIP work?

The Road Services Division Capital Improvement Program (CIP) contains all design and construction and studies for improvements on roads, bridges or transportation facilities in the unincorporated areas of King County. We have a glossary to help explain our terms and jargon.



Budget and Funding

Project supervisor

Tim Lane
206-477-3543